25m Pool construction ongoing

Date: 1 November 2013

The steel reinforcing is in place, the concrete floor is poured, spread, and then troweled smooth by hand.

Pools take approximately two months to build. The concrete pool construction process includes;

  1. Set out and pre-start meeting
  2. Delivery of materials for form work
  3. Earthworks and hole digging
  4. Formwork and steel placement
  5. Concrete shell pour
 
The next few stages will include:
  1. Backfill and plumbing
  2. Electrician
  3. Waterline tiling
  4. Step treads
  5. Bull-nose header on pool edge
  6. Water features and paving
  7. Filtration equipment delivery
  8. Shell clean out and plaster delivery
  9. Internal finish application
  10. Fill with water
  11. Chemical treatment
  12. Client instruction and handover


Caption The steel reinforcing is in place, the concrete floor is poured, spread, and then troweled smooth by hand.